The project, spearheaded by Quinbrook and supported by core supplier CATL, has now secured approximately A$1.2 billion in total financing across its first three stages. Stage 2 has officially entered commercial operation, meeting delivery targets despite the technical hurdles inherent in utility-scale energy storage. The campus sits adjacent to the South Pine substation, a strategic location that provides 4,000MW of connection capacity and favorable marginal loss factors for the Queensland power grid.
Technological consistency remains a priority for the build-out. While Stages 1 and 2 utilize CATL’s EnerC Plus liquid-cooled systems, Stage 3 will integrate the newer TENER S platform. These units allow for high-density, back-to-back installation, shrinking the required footprint by roughly 20% compared to previous iterations. Beyond hardware, a Long-Term Service Agreement ensures that CATL manages condition monitoring and preventive maintenance for the duration of the asset's lifecycle.